Use Dovico Planning & TimesheetDovico Timesheet's Microsoft Project Server Link to link project and task assignments created in Microsoft Project Server to Dovico Planning & TimesheetDovico Timesheet. When a link is created, employees use Dovico to track time on the task assignments created in Microsoft Project Server. When time entries are submitted and approved, the actual hours worked are updated in Microsoft Project Server files.
Click here to see an overview of the information being transferred using the Microsoft Project Server Link.
This topic describes the fundamental steps required to setup and synchronize data from Microsoft Project Server to Dovico Planning & TimesheetDovico Timesheet. Details on how to send time entries from Dovico to Microsoft Project Server are described in Send time to Microsoft Project Server.
STEP 1: Establish the connection to Microsoft Project Server.
STEP 2: Synchronize the Resource pool.
STEP 3: Synchronize projects, employees and task assignments from the Microsoft Project Server file.
Prerequisite:
The Microsoft Project link requires ActiveX controls and only Internet Explorer supports ActiveX. Limited functionality is possible for Microsoft Project Server using Firefox and Chrome web browsers.
Notes:
|
STEP 1: Establish connection information
Select Microsoft Project from the menu (Menu > Views tab > Microsoft Project).
Select the Project Server Link tab.
In the Connection Information area, enter the Microsoft Project Server URL.
Select your login Authentication format.
Note: The Windows Authentication option cannot be used by customers on Dovico's Hosted services. |
Enter the Microsoft Project Server Authentication User name and Password.
Click the Apply button.
Warning: Before moving to the next step, you must ensure that you have added a Microsoft Project Server Account in Microsoft Project under Tools, Enterprise Options, Microsoft Office Project Server Accounts. After which you are prompted to connect to a Microsoft Project Server Account each time you access Microsoft Project. |
STEP 2: Synchronize the Resource pool
When a Microsoft Project Server resource pool is linked to Dovico Planning & TimesheetDovico Timesheet, employees assigned to each project are automatically added to the Dovico database.
Warnings:
|
Start Microsoft Project Server.
From Dovico Planning & TimesheetDovico Timesheet, select the Project Server Link tab.
Click the Get Resources button located below the Resource list box.
Microsoft Project Server |
|
Dovico |
Resource first name |
Employee first name |
|
Resource last name |
Employee last name |
|
Resource email address (optional) |
Employee email address |
For each employee added, you need to edit their User ID and Password information as random data is entered in these fields when an employee is added from the resource pool. You also need to modify the Software access field for each new employee as 'None' is selected by default. Use either the Project Assignment view's employee list or the Items List - Employees view to edit this information.
Note: If a synchronized employee in the Microsoft Project Server resource pool file is ever deleted, that employee will remain in the Dovico database. |
STEP 3: Create a link in Dovico Planning & TimesheetDovico Timesheet
After the link is successfully created:
The project is added to the list of projects in Dovico. You can edit some project information in Dovico without affecting the link or Microsoft Project Server files.
Tasks are not added to the list of tasks in Dovico. However, the tasks are displayed in the Project Assignments view and are available to employees entering time.
Prerequisite:
Dovico Planning & TimesheetDovico Timesheet only supports task assignments from the bottom level tasks in the Microsoft Project Server file. Also, do not leave any blank rows in the Microsoft Project Server file's Gantt chart view. Additional details
Click the Add Project button located below the Project list box.
A pop-up window opens listing all Microsoft Project Server projects not currently linked to Dovico.
Select a project from the list and click OK.
The project, its tasks and assignments are added to Dovico. The project (with the "published" extension) and its tasks are displayed in the Project Assignments view. You cannot add or edit assignments using the Project Assignments view.
Microsoft Project Server |
|
Dovico |
Projects |
Projects |
|
Tasks |
Tasks |
|
Resource Assignments |
Task Assignments |
|
Work |
Estimate hours |
|
Assignment Start and Finish dates |
Assignment Start and Finish dates |
|
WBS code (optional) |
WBS code (displayed in Budgeted Time & Costs view) |
|
Publish (optional) |
Show/Hide feature in Project Assignments view |
The project assignments are now created in Dovico Planning & TimesheetDovico Timesheet and employees can begin tracking their time against this project.
Click here to see how to send time from Dovico Planning & TimesheetDovico Timesheet to the Microsoft Project Server file.
Notes:
|