ETC

The ETC column (Estimate to Complete) displayed at the far right of the timesheet grid is an optional column you can use to enter how many hours you estimate are required to complete the task.

 

ETC values are sent to the database and enable managers to view estimated time to completion reports to aid in tracking project development and employee efficiency.

 

 

Notes:

  • The ETC column can be hidden. See Options.

  • ETCs can be adjusted by managers using the Budgeted Time & Costs view.

  • Historical ETC values are not saved. The ETC value entered for a task in a given week appears in all previous and future weeks.

  • ETCs are not submitted along with time entries but are immediately updated in the database whenever an ETC value is added or modified.

  • When an ETC value of 0 is entered for a task, it is displayed as "Complete" in various administrative views and reports.

  • The ETC value is also displayed in the Time Entry Details area (Task Progress Information).